@thesis{thesis, author={Pahiyanti Novi Gusti and Tangkilisan Axl Brian Androcles}, title ={PERENCANAAN PEMBANGKIT LISTRIK TENAGA SURYA DI POS PENGAMATAN GUNUNG SOPUTAN}, year={2019}, url={http://156.67.221.169/1341/}, abstract={This planning is based on the need for electricity that must be non-stop which is distributed at the post observation of Soputan mount, this is because the need for electricity is very important in seeing the movement of the Volcano. This plan costs Rp. 80.584.534 with a planned load of 18,04 kWh. For such loading, 20 solar panels are used with a capacity of 200 Wp, and for solar charger controller (SCC) used 2 pieces with each SCC used for 10 solar panels. As for the battery used as many as 3 pieces with each battery has an energy of 2.4 kWh, then for the inverter using an inverter with a power of 2650 W. For this planning is said to see from the performance ratio produced by 84%.} }