@thesis{thesis, author={fadillah Jihan and Handayani Oktaria}, title ={Perbaikan Jatuh Tegangan pada Jaringan Tegangan Rendah Gardu CPD 51 dengan Penambahan Gardu sisip pada Penyulang Magister UP3 Cikokol}, year={2022}, url={http://156.67.221.169/5283/}, abstract={In the electricity distribution system, good service quality must always be provided. One example is providing a good voltage value to customers and the absence of voltage drop disturbances. Based on SPLN No. 1: 1978, the maximum service voltage is 5% and the minimum is 10% of the ideal nominal voltage of a low-voltage network, which is 220 Volts. One of the locations experiencing voltage drop disturbances is the Kali Bawah Poris Indah Cipondoh Irrigation area. Based on the results of the analysis that has been carried out by the network division officer of PT PLN UP3 Cikokol, it turns out that the voltage drop that occurred in the Kali Bawah Poris Indah Cipondoh Irrigation Area was caused by the distance of the location from the CPD 51 substation that supplies electricity, the distance is 630 meters. Then, the area around the location also has high loads due to the large number of residential settlements. Therefore, it is necessary to repair the area by using the load breaking method to a new substation. This method is done by moving the load on the old network to the new network, where the network that is moved is the last 21 poles in this direction, so that the load supported by one direction does not experience a voltage drop. The results obtained after breaking the load are the voltage on the receiving side increases to 220 Volt R phase, 219 Volt S phase, and 220 Volt T phase. Where previously the value of the voltage on the receiving side was the R phase of 190 Volts, the S phase of 192 Volts, and the T phase of 200 Volts.} }