@thesis{thesis, author={Novita Sari Dyana and Senen Adri}, title ={ANALISIS GRID IMPACT PENAMBAHAN PLTS 3x10 MWac PADA GI SEI HARAPAN DAN GI SEI BALOI TERHADAP JARINGAN KELISTRIKAN BATAM 150 kV}, year={2022}, url={http://156.67.221.169/5307/}, abstract={Batam City is currently targeted to have a Solar Power Plant (PLTS) with a capacity of 2.2GW where the PLTS to be installed is an On-Grid PLTS connected to the PLN electricity network, therefore it is necessary to conduct a study on the Electric Power System in the Electricity Area. Batam at the time of PLTS Interconnection. This study will focus on discussing Grid Impact after the addition of 3x10Mwac PLTS at GI Sei Harapan and GI Sei Baloi on the Batam 150kV Electricity Network. The Grid Impact observed includes a Power Flow Study in which there are Connection Drops and Channel Loss, Transient Stability Analysis after the addition of PLTS and the Raming Rate of the generator when the PLTS is in Loss Power condition. The results show that PLTS can cover a power supply of 30MW, there is an improvement in the voltage drop of +0.19kV at the Sei Harapan GI and +0.36 kV at the Sei Baloi GI. Can reduce the value of channel loss by 0,01MW so that the current channel loss becomes 0,28MW. The simulation results show that the voltage at the GI Sei Harapan and GI Sei Baloi has increased by 0.001 p.u and 0.002 p.u with a steady state frequency of 49.997 and the average active power at PLTG Tj Uncang 2 is 22.108MW. Then the Ramp Rate simulation shows that the active power supply by Tj Uncang 2 PLTG has increased by <10% of its capacity when the PLTS is in a Loss of Power condition and the time required to reach a stable condition when pursuing an active power supply is more than 2 seconds.} }