@thesis{thesis, author={Naksabandi Isroq Bahanudin and Pasra Nurmiati and Siregar Masbah RT.}, title ={PERENCANAAN PLTS UNTUK POS PENGAMATAN GUNUNG RINJANI}, year={2018}, url={http://156.67.221.169/773/}, abstract={This planning is based on the need for electricity that must be non-stop which is distributed at the post observation of Mount Rinjani, this is because the need for electricity is very important in seeing the movement of the Volcano. This plan costs Rp.99.774.200,77 with a planned load of 15 kWh. For such loading, 16 solar panels are used with a capacity of 200 Wp, and for solar charger controller (SCC) used 2 pieces with each SCC used for 8 solar panels. As for the battery used as many as 8 pieces with each battery has an energy of 2.4 kWh, then for the inverter using an inverter with a power of 3200 W.} }