@thesis{thesis, author={Hermawan Muhammad Rizal}, title ={Analisa Percepatan Proyek Menggunakan Metode Time Cost Trade Off (Studi Kasus : Proyek Pembangunan IGD, Instalasi Farmasi, Laboratorium dan Ruang Inap RS. Bhayangkara Nganjuk)}, year={2021}, url={http://repository.unik-kediri.ac.id/297/}, abstract={Project management is one of the things that has an effect in the smooth work of construction projects. Time and cost management is the benchmark in the successful implementation of the project. In the construction project of Bhayangkara Nganjuk Hospital, it includes construction work on IGD, Pharmaceutical Installation, Laboratory and Hospital Inpatient Room. Bhayangkara Nganjuk is indicated to have experienced delays due to unfaithful weather conditions. The delay will have an impact on the costs that will be incurred. The purpose of this research is to make an alternative time acceleration on the project by using the time cost trade off method. Acceleration is done by implementing a work shift system so that the results of time and cost are obtained after the work shift system is applied. The results of the study obtained the total cost after the acceleration of Rp. 3,873,505,632.00 the value is more expensive 11.25% than the normal cost of the project of Rp 3,481,698,000.00. With an acceleration duration of 125 days or 25.71% faster than the normal duration of the project of 180 days. From these results it is necessary to reconsider with the increase in the total cost of the project and the duration that has been done. Keywords: Project Acceleration, Time Cost Trade Off, Work Shift, Microsoft Project} }