DETAIL DOCUMENT
STUDI PERBANDINGAN PENAMBAHAN PLTMG 1X60 MW ATAU 6X10 MW TERHADAP SISTEM SULAWESI TENGAH
Total View This Week0
Institusion
Institut Teknologi Perusahaan Listrik Negara
Author
Saputra, Fatkhurahman Diyo
Hariyanto, Agung
Subject
Teknik Elektro 
Datestamp
2019-11-08 04:15:21 
Abstract :
Electrical problems always exist in modern human life. With population growth, the need for electricity will also increase, so that new power plants are needed. One of them is the addition of 60 MW PLTMG in the Central Sulawesi system. Therefore, it is necessary to study the power flow, the loss of power and short circuit to know the impact that will be caused by the system. This thesis discusses the addition of new PLTMG to meet the increasing burden on the Central Sulawesi system. With the help of ETAP software application, calculation of power flow, power loss and short circuit current in the system. 