Abstract :
Batam's electricity Load continues to increase every year, so power plants should
increase the supply of electrical energy to create a power balance between supply and
demand. Therefore PT. Brigth PLN Batam plans to install PLTS 50 MWAC on Batam's
20 kV electricity system. The installation of PLTS is conducted because it doesn?t produce
pollution and the energy is obtained free of charge. With the addition of PLTS, it can
affect the transient stability of the Batam?s electricity. Therefore, a generator lost, single
and double circuit lines were simulated, which was then studied on the stability of the
system frequency, Muka Kuning GI voltage and the rotor angle of the Tanjung Kasam
PLTU. In that study case, it remained stable even though it had swing a few second.
Beside that, the addition of this PLTS can also affect THD. It was obtained that the THD
value increased to 11.77% so that it passed the tolerance, which is a maximum of 5% for
voltage levels <66 kV. Therefore, a single tuned harmonic filter method is used to reduce
the THD value. After the method was applied, the THD value decreased to 4.27%.