DETAIL DOCUMENT
KAJIAN KELAYAKAN OPERASI PENGEMBANGAN SISTEM DISTRIBUSI 20 kV DENGAN MENGGUNAKAN APLIKASI ETAP DI PT PLN UP3 JAMBI
Total View This Week0
Institusion
Institut Teknologi Perusahaan Listrik Negara
Author
YUDI SAMUKTI, MARWAN
Sari, Dewi Purnama
Subject
Teknik Elektro 
Datestamp
2022-11-07 07:36:49 
Abstract :
The growth of electricity sales in Jambi province is projected to be 5.97 percent in 2021, 6.94 percent in 2022. With these problems, the overload problem of GI Payoselincah for Orchid, Dahlia, Leci, and Pokat feeders can be overcome by maneuvering feeders between GIs in Jambi city, namely GI Payoselincah, GI New Aurduri, GI Aurduri, and GI Sei Gelam. The method used is by estimating the growth of electrical energy from the results of processing the Simple-E application, and analyzing the power flow in the ETAP application. After the simulation, namely maneuvering the Dahlia feeder to the Johar feeder of 4.6 MW, Leci to Ketapang of 2.28 MW, Pokat to Sirih of 3.88 MW, and Orchid to GIS KJ of 6.4 MW, then the voltage drop on the Orchid feeder 19 .98 kV, Dahlia 19.97 kV, Lychee 19.92 kV, Pokat 19.94 kV, to Orchid feeder voltage 20.77 kV rose 3.91 percent, Dahlia 20.76 kV rose 3.93 percent, Leci 20, 74 kV up 4.08 percent, Pokat 20.74 kV up 3.99 percent, and technical losses for Orchid feeders by 19.3 kW down to 1.6 kW, Dahlia 4.2 kW to 1.7 kW, Leci 27, 1 kW to 6.5 kW, Pokat 18. 6 kW to 8.8 kW. From the simulation results, the feeder above has met the standards and is in accordance with SPLN 1 ? 1995. 
Institution Info

Institut Teknologi Perusahaan Listrik Negara