Abstract :
In the implementation of the Bengkalis Prapat Tunggal Road Improvement
project, it was very important to use heavy equipment to speed up the process of
carrying out work according to predetermined and planned targets. To get work
done on a project in a timely and economical manner by using heavy equipment
as a tool. The method used to analyze the productivity of heavy equipment work
in this study is Permen PU No 11 of 2013. The results obtained from each
productivity calculation are from ideal conditions or within an effective time of 8
hours, namely, Wheel Loader 82.17 m3/hour. Dump Trucks 30,110 m3/hour.
Motor Grader 60 m3/hour. Vibratory Rollers 136.95 m3/hour. Water Tank 83
m3/hour. Meanwhile, from the results of productivity calculations for real
conditions in the field or in real time, 5 hours, namely. Wheel Loaders 50,914
m3/hour. Dump Trucks, 30,396 m3/hour. Motor Grader 29,842 m3/hour.
Vibratory Rollers, 71.28 m3/hour. Water Tank, 48 m3/hour. The conclusion
above is for the smallest productivity in ideal conditions, namely Dump Truck
heavy equipment with a productivity value of 30,110 m3/hour and for Real
conditions in the field the smallest productivity is Dump Truck heavy equipment
with a productivity value of 30,396 m3/hour.