Studi Kelayakan Nilai Investasi Proyek Perencanaan Jembatan Pulau Bengkalis – Pulau Sumatra
Total View This Week0
Institusion
Politeknik Negeri Bengkalis
Author
Kurniawan, Fitrah
Subject
421 Teknik Sipil 
Datestamp
2024-08-24 07:33:17 
Abstract :
This study evaluates the investment feasibility of the Bengkalis Island - Sumatra Island Bridge project using the Net Present Value (NPV), Internal Rate of Return (IRR), and Payback Period (PP) methods. The analysis includes site selection using the Analytical Hierarchy Process (AHP) method, cost estimation, and revenue projection from toll tariffs. The results show that NPV>0, amounting to Rp.260.395.041.806. IRR> Discount rate, and Payback Period is projected to occur in 2080, faster than the economic life of the project, so based on the Feasibility Study of investment Value, it can be concluded that the construction of the Bengkalis Island - Sumatra Island Bridge is feasible. 