Abstract :
Clean water is the background for analyzing the development of
clean water in Bangsri village. Namely by knowing the discharge of clean
water, the need for clean water for the next 10 years, planning the capacity
and dimensions of the ground reservoir.
With the current deep well and considering that the population is
increasing every year, the volume of water discharge required is increasing.
With this clean water development analysis, it is targeted that the
community's clean water needs can be met with a service level of up to
100% of the population of Bangsri Village in the future.
The calculation of the projected population from 2019 which is
1,917 to 2029 is 2,088 people, with the need for water until 2029 is 2,088
liter/second. It is planned that the ground reservoir with a capacity of
168,584 m for the two reservoirs will become 84,288 m with dimensions
of 5.00 x 3.00 x 3.5 meters using a concrete plate construction and
functioned as a filter as well as deposition.