Abstract :
Karangan Village is one of the villages located in Bareng District,
which is divided into four hamlets, namely Jeruk hamlet, Blimbing hamlet,
Karangan Krajan and the hamlet of Karang Kulon. In Karangan village before
there is already a clean water system but it has not been able to meet water needs
clean the village to the maximum. Clean water system planning is done by
take advantage of the new springs which are then channeled through the system
gravity (gravity system) to the distribution reservoir, then the water is distributed to the
residents through a house connection (SR) with a gravity system. A number of
The formulation of the problem to be achieved in this study are: (1) Knowing
discharge from new springs, (2) Knowing the dimensions of the reservoir size
will be used, (3) Knowing the number of people who will get water. Data
What is needed in this study are: (a) primary data obtained from the results of
direct survey in the field (b) secondary data obtained from the agency
government or private sector to analyze the population that will be
get clean water. (c) with this plan the villagers
the essay can be met with water needs and immediately followed up by
related agencies/institutions, with relatively low investment costs and can
last for a long time. Results from research and discussion
obtained: (1) from the results of measuring the discharge of existing springs on average
has a flow rate of 0.628 ltr/sec. (2) after measuring the debit
springs, the number of people who will get clean water assistance
as many as 904 people. (3) with the spring discharge, the size of the spring is a determined
reservoir that is 3m, 1.5m wide, 2m high.